We are pleased to report continued progress on the installation of our new 3G pitch at Cheriton Road.

The latest phase of groundworks has moved forward nicely, with the drainage system now fully installed and 80% of the drainage stone laid. Once the stone is fully rolled and compacted, work will begin to make good the surrounding areas.

At the same time, our contractors, Velocity, will commence the next key phase — installing the shock pad layer and preparing for the application of the FIFA Quality Pro surface.

We will continue to keep you updated as each stage is completed. Thank you for your continued support as we work towards delivering a top-class facility for the club and the community.